Topical at the construction site

Infrastructure as well as auxiliary buildings and supporting buildings valued at EUR 400–500 million will be built at the Hanhikivi 1 construction site. See the video and photo gallery below to take a quick look at what is going on at the construction site.

At the moment, approximately 230 people are working at the construction site on any given day. The Sitemanager system includes 600 companies, of which 560 are Finnish. 3,000 people have passed the site access training. 

Construction of the nuclear power plant will start once Fennovoima has been granted a construction license for the plant. The nuclear power plant consists of a reactor building, a turbine building, a control room building, and fuel buildings, among others. The highest number of people involved in the construction of the nuclear power plant at a time will be around 4,000.

Contractor area for companies

Access permit to the construction site

Site access training for the construction site

Construction site visits


 

Construction site notifications

05.11.2019

Event for neighbors of the Hanhikivi 1 construction site and residents of the area on Tuesday, November 19, 2019

You are welcome to receive more information and discuss wintertime activities at the Hanhikivi 1 construction site at the Fennovoima training building on Tuesday, November 19, from 6 pm to 8 pm. Coffee will be served.The event is meant for neighbors of the Hanhikivi 1 construction site and residents of the area. The presentation will be given​ in Finnish.

Please enroll for the event by November 18: [email protected] or Kati Mehtomaa, tel. +358 20 757 8581.

At the event, Fennovoima’s Construction Director Jouni Sipiläinen, Site Environmental Manager Heidi Karjalainen and Radiochemist Mervi Söderlund will tell about the work at the construction site. 

17.05.2019

Water construction work will continue to south and north of Hanhikivi peninsula

BMGS Eesti filial will continue the dredging and water engineering works related to the port and the cooling water intake channel and backup intake channel structures to the south of the Hanhikivi peninsula. The dredging and water engineering works of the cooling water discharge structures to the north of the peninsula will also continue. Dredging mass will be moved to both the marine soil disposal area and the mainland. The marine soil disposal area is located some ten kilometers west of the Hanhikivi peninsula.

The dredging and excavation will cause local noise disturbance, as well as turbidity of the water in the working areas and in their immediate vicinity. Work plans and risk assessments have been prepared by paying special attention to mitigation of the harm caused by the turbidity and noise to the comfort of people in the area. Spreading of the turbidity in the water to the north of the Hanhikivi peninsula will be limited with a silt curtain. The silt curtain will extend 500 meters from the shore, and its location will be marked with buoys. According to the work plan, blasting will only be performed between 7:00 am and 10:00 pm.

The dredging and excavation will be performed from the mainland and the sea. The noise and the turbidity of the water will be monitored with continuously operating meters. Fishing in the construction areas and in their immediate vicinity will not be possible during the construction work.

Dredging will take place 24/7 as long as there is no ice cover. Underwater blasting may be performed between May 20 and October 10, taking into account the spawning period of fish. The work in the water areas will be performed in compliance with the water resources management permits and environmental permits from the Regional State Administrative Agency of Northern Finland. The permit decisions include regulations on the performance of hydraulic engineering works, fishery fees, compensation to commercial fishermen, and monitoring of the environment during construction, among other issues.

03.05.2019

Event for neighbors of the Hanhikivi 1 construction site and residents of the area on Tuesday, May 14, 2019

You are welcome to receive more information and discuss summertime activities at the Hanhikivi 1 construction site at the Fennovoima training building on Tuesday, May 14, from 6 pm to 8 pm. Coffee will be served starting at 5:30 pm. The event is meant for neighbors of the Hanhikivi 1 construction site and residents of the area.

Please enroll for the event by May 13: [email protected] or Kati Mehtomaa, tel. +358 20 757 8581.

At the event, Fennovoima’s Construction Director Jouni Sipiläinen and Site Environmental Manager Heidi Karjalainen will tell about the work at the construction site.

13.03.2019

Hanhikivi 1 power line project proceeds

Main lines between the future nuclear power plant and the national grid will be built in Fennovoima’s Hanhikivi 1 power line project. When considering all phases, the transmission line project will take some 8–10 years. Electrical energy produced by the future nuclear power plant will be transmitted to the grid via the power lines.

Two parallel 400 kV transmission lines will be built between the Hanhikivi peninsula and a new transformer substation to be built at Hanhela in the municipality of Pyhäjoki. Two parallel 110 kV transmission lines will be built between the Hanhikivi peninsula and a new substation to be built at Valkeus in the municipality of Pyhäjoki. The total length of the 400 kV power lines to be built will be some 21 kilometers and the total length of the 100 kV power lines will be some 19 kilometers. The power line route has been selected based on an environmental impact assessment report.

Fennovoima submitted expropriation and advance take-over application to the Ministry of Economic Affairs and Employment in February 2019. The company sent letters to the local landowners on the filing of the expropriation permit application. The Government will grant the permit on the basis of a proposal by the Ministry of Economic Affairs and Employment. Usually, the processing of expropriation permit takes from six to twelve months.

Agreements between Fennovoima and the landowners on the use of the land areas cover more than 90% of the properties along the transmission line route. The Ministry of Economic Affairs and Employment will request opinions from the landowners who have not signed an agreement with Fennovoima.

The right of use of the properties along the transmission line route will be reduced. Fennovoima will pay compensation to be determined by a expropriation committee for land areas is question. Fennovoima will receive a limited right to use the transmission line route for the construction, operation, maintenance and renewal of the transmission lines. The landowners will still own the land areas.

The construction schedule for the transmission lines follows the schedule of the nuclear power plant project. According to the plan, the transmission lines will be built between 2020 and 2026 in such a manner that the 110 kV transmission lines will be commissioned in 2024–2025 and the 400 kV transmission lines in 2025–2026.

Once complete, Hanhikivi 1 will produce Finnish emission-free electricity at a stable price for at least 60 years.

Movement restriction

There is a movement restriction imposed by the Ministry of the Interior for the construction site on the Hanhikivi peninsula. The restricted area covers the land areas owned by Fennovoima and the water area limited by the construction site.
The restriction has been imposed in order to secure the operations and the property at the construction site, as well as to protect the people working there. Anybody violating the restriction can be ordered to pay a fine.

Aviation prohibition at the Hanhikivi peninsula

Aviation at the Hanhikivi peninsula construction site has been prohibited by a Government Decree. The aviation prohibition area covers the fenced-in construction site area on the Hanhikivi peninsula and the surrounding land and water areas in the immediate vicinity of the construction site. Aviation is only allowed if it is connected to the maintenance of the future Hanhikivi 1 nuclear power plant or specifically connected to its operation.